Discount the future payoff at the rate the money could earn elsewhere. If the present value beats the €10m outlay the net present value is positive and the project is worthwhile. The rate at which NPV is exactly zero is the internal rate of return. Question 1, from Business Economics (Mankiw, Taylor & Ashwin, ch. 19).
Investing elsewhere grows to
Present value of payoff
Net present value
Internal rate of return
Two views of the same decision. Compounding the outlay forward (PV × (1 + r)ⁿ) and discounting the payoff back (FV ÷ (1 + r)ⁿ) always agree. NPV falls as the discount rate rises because a higher rate makes future money worth less today.